Boathouse Alterations

 

Visit main RNLI site

 

Boathouse Alterations

Photos taken by Rhodri Jenkins

RNLI Project Supervisor

Click on photo to enlarge

 

 

Week ending 28/6/08

Boathouse floor slab cut for removal



Removal of the cut floor slabs
Crew room works continue
Continue to cut the next section of Boathouse slab

 


Week Ending 21/6/08
Trial assembly of precast concrete toe units


New section of slipway installation
New section of slipway installation
New section of slipway installation
New section of slipway installation

 


Week ending 14/6/08

Jackup barge being moved to new position

Old section of slipway being removed
Core drilling to the boathouse columns
Old slipway now fully removed
Delivery of new slipway steelwork
Start of the boathouse slab cutting

 


Week ending 7/6/08

Existing slipway transom prepared for new paint system
New paint system applied to the existing slipway transoms
Installation of the next slipway section
Installation of the next slipway section
Installation of the next slipway section