Week ending 30/8/08

Steel fixing to Boatwell slab
Steel fixing to Boatwell slab
Scaffolding set up to Boathouse for crew room works
Slipway adaption works continue

 


Week Ending 23/8/08
Falsework to new boatwell slab
Falsework to new boatwell slab
Slipway adaption installation
Slipway adaption installation

 

Week Ending 16/8/08

Adapted slipway units installed
Views of Boathouse slab now fully removed
Views of Boathouse slab now fully removed
Views of Boathouse slab now fully removed

 


Week Ending 9/8/08
Last section of Boathouse floor now removed
Aerial view of the end of the slipway with all PC units in place

Scared of heights?
Installation of the adapted slipway section
Bargeworks now complete, so now tugged off site

 


Week Ending 2/8/08
Mechanics workshop dismantle
Cutting works to main beam
Section of main beam following cutting works
Final section of boathouse floor being cut for removal

 